Investments

Projects in progress

---

Projects completed

ÇWe signed a supply contract about 120 ton/hour capacity electronic rotary scales with Haver & Boecker company to increase our cement packaging and loading capacity. Facility/plant has been operating since 2016 and so our loading capacity has been increased.

Packaging Unit Installation Investment for 1st Cement Silo in 2014 - 2016:

In 2015, an agreement was signed with FLS company by means of upgrade of total 4 filters to bag type filters. In 2015 our company finished upgrades of 3 electro-filters and 1 gravel filter to bag type filters in order to minimize dust emissions down to 10 mg/Nm³ as environmental awareness of our company.

Installation investment of converting electro Electro-Filters and Gravel Filters to Bag Type Filters in 2015:

For electricity saving, our company uses waste heat recovery system which uses waste heat coming from production process. The company signed an agreement with Chinese Catic company on 21 April 2014 to build a 12 MW/hour capacity waste heat recovery power plant.

On 26 November 2015 the system started to generate electricity and right now the system meets 21% electricity requirement of Goltas.

Financers of this project are European Bank for Reconstruction and Development(EBRD) and Turkish Sustainable Energy Financing Facility(MidSEFF). "The most energy efficient project" financed in Turkey and also granted award by EBRD. Recovered energy from the waste-heat project can supply up to 15.000 houses.

Waste Heat Recovery Power Plant Project in 2014 – 2015:

Purchase agreement of 230 ton/hour capacity vertical cement mill was signed with Loesche on 22 July 2013. Plant started up on 07 August 2015.

Minimizing energy consumption per ton, savings are acquired by decreasing production costs of cement.

5th Cement Mill Installation Investment in 2014 – 2015:

For 3rd cement mill capacity increase an agreement was signed with Pollysıus company.

Capacity is increased over 50% and per every ton of cement production 13 kWh energy save has been achieved.

3rd Cement Mill Capacity Increase Investment in 2013 – 2014:

Low cost transportation is achieved by train station investment. The train station has loading and unloading platforms to facilitate raw material and product transportation via rail road.

Goltas Train Station Installation Investment in 2008 – 2009:

2 new 100 ton/hour capacity rotary scales were purchased to increase our cement packaging and loading capacity. Additionally new cement delivery system between silos was built.

5th Cement Silo Extra Packaging Unit Installation Investment in 2008 - 2009:

In 2005 Goltas and Aumund companies agreed on building 75.000 tons stock capacity closed clinker silo and delivery lines.

5th Closed Clinker Silo and Clinker Transfer Line Installation Investment in 2005-2007:

Our factory fed by 45MVA power from 66kV distribution network can consume 62.5 MVA power from 154kV transmission network by means of Goltas Transformer Center which is a new energy supply system investment and was commissioned on 11.05.2016. With this investment, additional power required for capacity increase was met, high quality energy level acquired by minimizing effects of power loss due to oscillation in the supply network and also company earned money because no distribution network cost was paid. 154/6,3kV - 50/62,5 MVA Goltas Transformer Center and distribution line are still used actively.

154/6,3kV Transformer Center and Energy Transfer Line Investment in 2005-2006:

An agreement was signed with Loesche company in order to enlarge raw mix (farin) mill production capacity to 120 ton/hour from 90 ton/hour.

2nd Raw Mix(Farin) Mill Unit Modernization in 2005:

An agreement was signed with FLS in order to acquire electro-filter instead of low capacity Walter electro-filter. New filter usage has started in 2007.

1st Line Electro Filter Capacity Increase Investment in 2002-2007:

An agreement was signed with KHD on 19 April 1998 in order to increase 2000 ton/day capacity of 2nd line to 4000 ton/day capacity. 600.000 ton increase in Clinker production has been achieved. Unit cost of 1 kg clinker is decreased as 850 kcal/kg energy requirement decreased to 780 kcal/kg.

2nd Line Cement Plant Pre-calcination Capacity Increase Investment in 1998-2006:

In parallel with 3rd raw mix(farin) mill project, 10.000 ton stock capacity raw mix(farin) homogeneous silo was built. Raw mix(farin) is homogenized with new technology and this increased quality in clinker production. At the same time raw mix(farin) silo which is planning to be built in the future and required for 2nd cement line capacity increase project, is ready.

3rd Raw Mix(Farin) Homogeneous Stock Silo Installation Investment in 1996 – 1999:

220 ton/hour capacity raw mix(farin) mill was built to increase raw mix(farin) capacity which affects 2nd clinker production line. When electricity costs more in times of the day the production can be easy by easing raw mix(farin) production so a lot of money saved. Also raw mix(farin) necessary for 2. cement line capacity increase which is planning to be built in the future, is produced.

3rd raw mix(farin) Mill Unit Installation Investment in 1996 – 1999:

Cement was transferred to silos with high pressure air generated by compressors,

By this investment, cement is transferred to silos via air slide and bucket elevator. Also, electricity consumption has been seriously decreased.

Project was completed in December 1997 and was commissioned.

Cement Air Slide Transfer System Installation Investment in 1996 – 1997:

10.000 ton stock capacity cement silo was constructed. In this facility, there are 2 cement packaging facilities each has capacity of 100 ton/hour and 2 cast cement loading facility. Loading capacity is increased 67% and stock capacity is increased 100%. Facility was completed in December 1997 and started production.

5th Cement Silo and Packaging Unit Installation Investment in 1996-1997:

Clinker shipments become easier thanks to this project and this line also by serving in clinker sale, facilitates loading.

Clinker Transfer System Installation Investment in 1994-1996:

Increasing Cement grinding capacity and stopping production hours when electricity is expensive by the help of 140 ton/hour capacity cement mill allowed company adopt cost efficient production model.

4th Cement Mill Installation Investment in 1993-1997:

As a result of 1st line clinker production capacity increase, cooling unit automation and modernization was completed and it has been working since February 1995.

1st Line Clinker Cooling Unit Modernization in 1993-1994:

To increase capacity of present 1st and 2nd cement mills by 50%; new pre-crusher placed in front of mills, new separators were supplied and mills were modified. Polcom pre-crusher started operation after modifications and automation processes are completed.

1st Cement Mill and 2nd Cement Mill Capacity Increase in 1992 -1995:

Tender was initiated for cement factory planned to produce 1700 ton clinker daily and 600.000 ton/clinker annually. Plant started production on 27 June 1992. With this project, clinker production in 2 production lines capacity reached 1.200.000 ton/clinker annually.

2nd Line Cement Plant Installation Investment in 1987-1992:

Gravel Filter was supplied from Lurgi instead of multicyclone filter which has low dust removal efficiency. Gravel Filter started operation in 1989.

1st Line Gravel Filter Investment in 1987-1989:

1.700 ton/day clinker production capacity to 2.300 ton/day capacity increase project was awarded to Polysıus.

In order to finish the project, long term stand was necessary. But as intense market requirement plant did not stop production. The project was started when 2nd clinker production line start operating in February 1995. 1st line clinker production capacity was increased as 25%

1st Line Cement Plant Capacity Increase Project Between 1986 – 1995:

It was decided to purchase a 70 ton/hour capacity cement mill in 1985. The mill started operating in 1986.

3rd Cement Mill Installation Investment in 1985 - 1986:

Plant to use low cost coal instead of high cost fuel oil in rotary kiln was established. So that establishment achieved huge savings by transforming 100% of fuel into coal compared to fuel oil.

1st Line Coal Mill Installation Investment in 1983-1984:

Cement Plant started production on 12 April 1973 with the aim of daily 1700 ton clinker production and annually 600.000 ton/clinker production.

1st Line Cement Plant Installation Investment in 1969-1973: